Paving Area Calculator: Measuring Area & Sand Required

DIY Paver Brochure | Preparing The Area

We can help you to work out what you need. Before beginning, it is important to have a clear plan worked out.

First things first.

Pavers can usually be laid around your house without council approval. However, if you’re doing a driveway or working in an area where your paving encroaches onto council verges, you may need to contact your local council. Some of the newer residential communities have covenants covering the use of driveway material. If so, get authorisation before proceeding.

The first step is knowing the exact dimensions of the area to be paved. Measure out your area and mark with string or paint. Once you have measured and measured again, you can start to draw up your plan.

The quantity of the materials needed for the paving job depends upon the total area to be paved. This can be determined from measurements taken off the plan or if the area to be paved has been pegged out on site. The area is simply calculated by measuring the width and length of the area to be paved.

The open-secret is to break it into sections. Below are helpful diagrams to help you figure out the total area of your surface.

Area Calculator

The calculation for the materials needed will depend on the type of materials you will most likely need for your paving surface. We’ve broken it down for you below.

How many pavers will you need? Calculate the square metre to be covered and add 5% to allow for cuts and wastage (only 2% should be required for wastage on jobs greater than 100m2).

Area to be paved ____ (m2) x 1.05 (allows for 5% wastage) = _____ total m2 of pavers required

Remember: Deduct the total m2 of header course paved from the total m2 of pavers required when ordering.

For every 100mm depth of roadbase material required to prepare the paved area, allow 1 tonne of road base material for every 6m2 of the area to be filled.

Area to be paved ____(m2) x 0.167 (allows for 100mm thick roadbase) =____ tonne of roadbase required

30mm of bedding sand (washed concrete sand) is required under all paving. 1 tonne will cover approximately 15m2.

Area to be paved ____ (m2) x 0.05 (allows for 30mm thick bedding sand) = ____ tonne of bedding sand required

Jointing sand is used to fill the gaps between the paving units once laid. A 40kg bag will cover approximately 15m2 ,of paving depending upon the size of joint spaces.

Area to be paved ____ (m2) x 0.067 (allows for 3mm joint spaces) = ____ kg bags of jointing sand required

Paving not abutting another structure will require a concrete restraining strip, a quarter of a cubic meter of concrete will be required for approximately 50 lineal metres of edge restraint.

Length of edge restraint ____ (m) x 0.005 (allows for 100mm triangular edge restraint) = ____ m3 of concrete required

When planning, make sure you allow for stormwater runoff and think about any other services you may want to be laid under the paving, such as irrigation or electrical for lighting before you begin.

Visit us at APC to pick up a free sample!

Or, send us a product enquiry or request a quote online